June 21: Progress Update

• Blue Paint Under Awning Begins
• Cabinet tops & pulls installed in Coffee Bar Area

Comment

June 17: Progress Update

Comment

June 17: Progress Update

• ADA Compliant Ramp to Building Entrance Completed
• Gates Installed In the Parking Lot as a safety measure to prevent cars from speeding through the lot
• Kid's "Pipe" Decor installed - ready for paint
• Coffee Bar received 1st coat of sealer
• Coffee Bar Cabinetry Painted

Comment

June 16: Progress Update

Comment

June 16: Progress Update

• Coffee Bar In Progress
• Exterior Paint In Progress
• Kitchen In Progress
• Kid's Ministry Decor In Progress
• Bathroom/Classroom Hygiene Accessories Installed
• HVAC Ducts Installed in Worship Center
• TJ's Prayer Preserved with Green Paint

Comment

Comment

Pouring the Stage

• Pouring the Concrete Stage
• Trenching the Plumbing Lines
• Installing the Sprinkler Systems

Comment

June 6: Dennis Joining In the Fun!

Comment

June 6: Dennis Joining In the Fun!

Yikes! That's right... we put Dennis behind the wheel of this beast! Check out the video below of Dennis knocking out the curtain walls under the Family Entrance awning to open it up and make the entrance safer and visible. Good Job Dennis!

Comment

May 27: Progress Update

Comment

May 27: Progress Update

• All Walls Now Completed & Painted
• All Lighting Installed
•All Restroom Plumbing & Stalls Completed
•HVAC Completed